DARIEN, CT — Darien's summer paving program is set to begin this week.
Drivers should consider adjusting their routes if necessary and exercise caution. Preparatory roadwork will begin before the paving date. Road surfaces are expected to have raised structures, according to the town.
Subscribe
Here is the paving schedule:
- Bittersweet Lane from Middlesex Road to cul-de-sac - milling to start Aug. 6, with paving to finish Aug. 12.
- Nutmeg Lane from Hollow Tree Ridge Road to Darien High School - milling to start Aug. 6, with paving to finish Aug. 12.
- High School Lane from Middlesex Road to Darien High School - milling to start Aug. 6, with paving to finish Aug. 13.
- Midbrook Lane from Leroy Avenue to cul-de-sac - milling to start Aug. 7, with paving to finish Aug. 13.
- Kona Road from Leroy Avenue to cul-de-sac - milling to start Aug. 7, with paving to finish Aug. 13.
- Mystic Lane from Leroy Avenue to cul-de-sac - milling to start Aug. 7, with paving to finish Aug. 13.
- Knollwood Lane from Mansfield Avenue to cul-de-sac - milling to start Aug. 10, with paving to finish Aug. 14.
- Saint Nicholas Road from Mansfield Avenue to cul-de-sac - milling to start Aug. 10, with paving to finish Aug. 17.
- Fox Hill Lane from Mansfield Avenue to cul-de-sac - milling to start Aug. 11, with paving to finish Aug. 18.
- Bridle Trail from Hollow Tree Ridge Road to cul-de-sac - milling to start Aug. 12, with paving to finish Aug. 18.
- Hancock Lane from Hollow Tree Ridge Road to cul-de-sac - milling to start Aug. 13, with paving to finish Aug. 18.
- Camp Avenue from Hollow Tree Ridge Road to Jackson Place - milling to start Aug. 13, with paving to finish Aug. 19.
- Briar Brae Road from Hoyt Street to Briar Brae Road - milling to start Aug. 14, with paving to finish Aug. 20.
- Wilson Ridge Road East from Wilson Ridge Road to cul-de-sac - milling to start Aug. 17, with paving to finish Aug. 20.
- Wilson Ridge Road from Hollow Tree Ridge Road to Hollow Tree Ridge Road - milling to start Aug. 17, with paving to finish Aug. 20.
- Linden Avenue from Hollow Tree Ridge Road to Gardiner Street - milling to start Aug. 18, with paving to finish Aug. 21.
- Hollow Tree Ridge Road from Railroad Bridge to West Avenue - milling to start Aug. 18, with paving to finish Aug. 21.
- Noroton Heights Railroad Station from Heights Road to Heights Road - milling to start Aug. 18, with paving to finish Aug. 21.
- Heights Road from Hollow Tree Ridge Road to Edgerton Street - milling to start Aug. 18, with paving to finish Aug. 24.