Middlefield Firehouse Committee Approves $101,209 In Expenses, Reviews Construction Schedule
Middlefield firehouse officials extend a project management contract, approve equipment spending and review construction progress.
MIDDLEFIELD, CT — The Middlefield Public Safety and Firehouse Building Committee approved a $53,560 contract extension for project management services and authorized up to $40,000 in equipment purchases during its Nov. 18 meeting.
The approvals came as contractors continued to target the end of December for completion of the new building portion of the project, with officials exploring ways to accelerate the overall construction schedule.
Project Management Contract Extended Through June
The committee approved extending its contract with Arcadis through June 4, 2027, at an additional cost of $53,560.
Find out what's happening in Durham-Middlefieldfor free with the latest updates from Patch.
The extension provides for 12 combined hours of project management services per week over 26 weeks.
Committee member Kevin Boyle introduced the motion, with Ryan Colwell seconding. The motion carried.
Find out what's happening in Durham-Middlefieldfor free with the latest updates from Patch.
The committee also authorized equipment purchases not to exceed $40,000 for computers, telephones, printers and other equipment needed throughout the public safety facility.
Colwell introduced the motion, with Boyle seconding. The motion carried, with final purchases subject to committee review.
An equipment planning spreadsheet attached to the meeting minutes identifies $95,306.10 in potential purchases, including communications equipment, workstations, networking infrastructure and radios.
The committee requested detailed equipment information to establish spending limits and allow purchases as needed.
Construction Progress And Potential Schedule Improvements
Owner's representative Zachary Machold presented updates on construction and proposed furniture purchases for both phases of the project.
Contractors reported progress on exterior concrete and site work, with grading and asphalt installation expected to follow.
A tank has been installed and passed testing. Interior drywall, electrical wiring, siding, trim and gutter installation were also progressing.
Full electrical service remains dependent on an inspection by Eversource. Fire Chief Peter Tyc plans to contact the utility to expedite the inspection.
The construction team continues to target the end of December for completion of the new building.
Scott Bracey is expected to present a recovery schedule at the committee's next meeting, with the goal of moving the anticipated project delivery date to May 2027 rather than June or July.
Equipment Installation Presents Design Challenge
The construction team identified a problem involving the installation of a Solo Rescue washer.
The equipment requires a 38-inch doorway, but the existing opening measures only 36 inches. Officials discussed modifying the door frame or replacing the door to accommodate the equipment.
The committee also reviewed room numbering, signage and flooring samples.
Members expressed a preference for a glossy red flooring finish over a matte alternative, with additional review of the samples planned during daylight hours.
Officials also discussed preparing a mock-up of the building's exterior Middlefield lettering to ensure it fits properly along the angled facade.
Communications And Radio Room Expenses Approved
The committee approved several additional project expenses:
- $4,195: Falcon Public Safety Solutions invoice No. 1114 for mission-critical communications connectivity and related public safety support services. The company was identified as the sole-source vendor.
- $3,330.58: Millcraft Change Order No. 1, dated Nov. 12, for radio room countertops.
- $123.50: October administrative services provided by Tina Olszewski.
All three motions carried.
Including the Arcadis contract extension and the equipment spending authorization, the committee approved expenses and spending authority totaling $101,209.08.
Temporary Road Closure Discussed
Officials raised concerns about the location of a 2,000-gallon tank near a public roadway and the need to protect associated hoses.
The discussion included the possibility of closing the roadway for two to three weeks. No formal road closure was approved.
Tyc also recommended closing the building's windows to reduce heating costs during construction.
Previous Meeting Minutes Approved
The committee approved its Oct. 9, Oct. 21 and Nov. 4 meeting minutes.
Five committee members attended the Nov. 18 meeting at 405 Main St..
Two members of the public attended but did not comment.
The meeting adjourned at 7:52 p.m.