PORTLAND, CT — The Portland Inland Wetlands Commission unanimously accepted an application to construct stairs, decking and a patio on a steep property overlooking Great Hill Pond, but deferred a decision on the proposed improvements until its December meeting.

During its Nov. 17 meeting, the commission also reviewed a state notice identifying deficiencies at a reservoir dam off Old Marlborough Turnpike and heard concerns from a resident about runoff and possible wetland alterations near the lake.

Great Hill Pond Access Project Under Review

The commission accepted Application #26-01 for 144 Great Hill Pond Road, where property owner Rebecca Miller proposes constructing stairs and landings between an existing home and dock.

Find out what's happening in East Hampton-Portlandfor free with the latest updates from Patch.

Matthew Pegolo, principal architect with PegArch Architects, said the property has an extremely steep slope that makes access to the dock difficult, particularly because the owner has limited mobility.

The proposed improvements include concrete stairs leading from a parking area to an existing deck, additional wooden decking and a small patio.

Find out what's happening in East Hampton-Portlandfor free with the latest updates from Patch.

The plans identify approximately 278 square feet of concrete steps, 276 square feet of permeable wooden decking and 293 square feet of concrete patio and steps leading toward a shed. They also identify approximately 576 square feet of concrete pavers.

Pegolo said the final section of stairs would be built of wood rather than composite decking because of cost considerations.

Commissioner Rebecca Esmi questioned how stormwater runoff would be managed with the additional concrete surfaces and whether measures would prevent construction debris from entering the lake.

Pegolo said protective fencing would be installed around the construction area.

Inland Wetlands Agent Jim Sipperly said he had inspected the property and observed significant erosion caused by the steep slope and an existing loose-gravel walkway.

Commissioner Mitchell Gilbert asked whether the improvements would reduce runoff impacts compared with existing conditions. Sipperly said they would.

Gilbert also questioned the commission's jurisdiction because no work was proposed within the wetlands boundary.

Sipperly explained that the proposed work falls within the 100-foot upland review area, which is subject to commission oversight.

Pegolo said the project has been under development for approximately three years and estimated construction would take four to five weeks.

Sipperly recommended that commissioners interested in inspecting the property arrange individual site visits.

Robert Wildermuth moved to accept the application, with Gilbert seconding. The motion passed unanimously.

The vote accepted the application for further review; it did not authorize construction. The commission is expected to continue considering the proposal in December.

State Inspection Identifies Reservoir Dam Deficiencies

The commission reviewed correspondence from the Connecticut Department of Energy and Environmental Protection's Dam Safety Unit concerning a dam near the reservoir off Old Marlborough Turnpike.

According to the meeting minutes, a state inspection identified several deficiencies at the dam.

The correspondence requested acknowledgment from the town that the deficiencies had been identified and would be addressed.

The first selectman and Sipperly had signed the correspondence.

The commission took no recorded vote on the matter.

Resident Raises Concerns About Wetland Changes Near Lake

During public comment, resident Norm Ward raised concerns about drainage, vegetation removal and activities affecting the area around Great Hill Pond.

Ward described a neighboring property where a watercourse drains toward a roadway, enters a catch basin beneath Great Hill Road and eventually discharges toward the lake.

He said heavy rainfall sends water through the storm drainage system and into the lake.

Ward also questioned work on a neighboring property where he said a lawn had gradually expanded into an area containing wetlands.

He said dead trees had previously obstructed water flow and that Sipperly had advised the property owner to remove obstructions to improve drainage.

Ward contended that the work went beyond the original discussion, including removal of wetland vegetation and excavation of a ditch to collect runoff.

He expressed concern that the changes reduced the area's ability to retain water and directed runoff toward the lake.

Esmi asked whether the commission had authority to address the concerns.

Sipperly said the wetlands remained present and that he had previously authorized the property owner to clean up the area.

He agreed to revisit the property and take photographs to document current conditions.

No violation was established or enforcement action taken during the meeting.

Ward also asked about previous complaints involving golf balls being hit into the lake.

Sipperly said he had contacted the property owner, who indicated the activity would stop. When a later complaint was received, Sipperly visited the property but found no one home.

He said there appeared to be no environmental impact and that enforcement would be difficult, noting that approximately two years had elapsed between complaints.

Ward requested additional follow-up.

Brownstone Park And Boat Launch Inspections Reported

Sipperly reported that work at Brownstone Exploration & Discovery Park appeared to be progressing according to approved plans.

He noted that a six-foot sidewalk around the parking area had not been installed as originally proposed. However, he said the missing sidewalk was a zoning matter rather than an issue for the Inland Wetlands Commission.

At the Carolina Drive boat launch, Sipperly reported that erosion-control measures had been properly installed. He said a proposed trail through a wetland area would require the applicant to appear before the commission and potentially retain a consultant.

Sipperly also discussed a body shop property on Glastonbury Turnpike where equipment is stored near a bank leading toward wetlands.

The current property owner, a landscaper, told Sipperly he did not intend to conduct work in the area and would contact the commission if plans changed.

Sipperly reported no current erosion or other problems at that location. He also said there were no wetlands violations or agent approvals to report.

Commission Approves 2027 Meeting Schedule

The commission unanimously approved its 2027 meeting schedule.

Meetings are generally planned for the first Tuesday of each month, with the November meeting moved to the third Tuesday because of Election Day.

Christopher Chenier moved to approve the schedule, with Esmi seconding.

The commission also unanimously approved its May 5, 2026, meeting minutes on a motion by Wildermuth, seconded by Gilbert.

Members noted that the Oct. 6 meeting lacked a quorum, so those minutes did not require approval.

Meeting Details

Chairwoman Martha Dumas called the Nov. 17 meeting to order at 7 p.m. at the Buck-Foreman Community Center, 265 Main Street.

Members present were Dumas, Esmi, Wildermuth, Gilbert and Chenier. Jeff Flynn, Margaret Keser and Town Planner Dan Bourret were absent.

Sipperly, Pegolo and Ward also attended.

The commission adjourned at 7:49 p.m. following a unanimous vote on a motion by Esmi, seconded by Wildermuth.