Setting the Record Straight on UI’s Misinformation Campaign
Sasco Creek Neighbors Environmental Trust, Inc response to opinion entitled "Should all of Conn. fund the Bridgeport/Fairfield project?"
By Andrea and Steve Ozyck, Co-Founders of Sasco Creek Neighbors Environmental Trust, Inc.
We appreciate United Illuminating’s recognition of the power of grassroots organizing—but Mr. Cole’s recent opinion piece entitled Should all of Conn. fund the Bridgeport/Fairfield project? misrepresents the facts and insults the intelligence of Connecticut residents. Worse, it attempts to pit communities against each other—exactly the opposite of what we should expect from a public service company. The piece is not only misleading, it’s divisive.
Our opposition to UI’s transmission line project through Fairfield and Bridgeport isn’t about “aesthetics.” It’s about respecting property rights, pure and simple.
Find out what's happening in Fairfieldfor free with the latest updates from Patch.
Let’s set the record straight.
UI’s overhead proposal would seize 19.25 acres of property via permanent easements—from our neighbors, our churches, our businesses, our parks, environmentally sensitive areas, and many irreplaceable sites listed on the National Register of Historic Places. And worse yet, those easements would be controlled by a foreign-owned company in Spain. Should we trust a company 3,500 miles away in another country to protect Connecticut’s neighborhoods, businesses, economic vitality, and heritage?
Find out what's happening in Fairfieldfor free with the latest updates from Patch.
We applaud UI for finally obtaining an independent undergrounding estimate for the Fairfield / Bridgeport project—but without any accompanying details, it’s just a number. There’s no clarity on whether it matches the scope and capacity of their overhead plan, what timeline it assumes (which significantly affects cost), or whether it reflects the most efficient, cost-effective route.
But here’s what we do know:
- UI has framed this project as a “necessary replacement” of aging infrastructure, yet their proposed design nearly doubles the current capacity—despite its own 10-year forecasts showing no significant increase in Connecticut’s power demand.
- This project is not for Connecticut. UI admitted on the record that the increased transmission capacity is designed to sell power to New York. Why should Fairfield and Bridgeport sacrifice land, property values, business development opportunities, and historic resources so UI can line its pockets selling power to another state?
- UI’s cost estimates don’t hold up.
- An independent property valuation expert found UI underestimated land acquisition costs by 3-5x, adding $90 - 150 million to the overhead project total.
- A 2022 CT Siting Council-commissioned study found the cost of undergrounding in CT averages $23 million/mile—less than one quarter of UI’s $100+ million/mile claim.
- UI padded its original $1B underground cost with $280 million in interest paid to themselves—largely because it assumed a 10-year construction timeline. Two independent experts–each with over 50 years of undergrounding experience–testified that the project should take no longer than 3 years, which would decrease the interest and total project cost by over $200 million.
- Even the Siting Council concluded that UI’s undergrounding was “overstated.”
- UI declined to seek federal funding that could have lowered costs for CT residents. Why? Federal dollars come with oversight—and transparency.
- UI misled the public about the need for the new giant monopoles, implying that the CT Department of Transportation asked them to move the existing lines off the Metro-North infrastructure. CTDOT has confirmed in writing that they made no such request.
- Mr. Cole accuses us of not balancing multiple perspectives. Well, by law the Siting Council is obligated to balance the alleged need for the project against environmental impacts – however inconvenient for UI. And when they did, in a straw vote, they rejected UI’s project and the very arguments Mr. Cole put forward in this article.
- Under new federal rules (FERC Order 1920), transmission project costs must be allocated to those who benefit. If New York stands to benefit from this project, New York should share in the cost.
- Other utilities have figured out how to deliver underground transmission in a cost-effective manner - why hasn’t UI?
- A 339-mile underground line from Canada to New York began in 2022 and is on track for completion in 2026, averaging $14 million per mile.
- Eversource’s Greenwich CT substation line project (2017–2019) installed 2.3 miles of double-circuit underground lines at $33 million per mile.
- Con Edison’s Queens project buried 6 miles of transmission lines in just 17 months (Jan 2022–May 2023) at a cost of $21 million per mile.
- UI hasn’t completed a high-voltage underground transmission project since 2008 and has limited undergrounding experience overall—likely the real reason behind its wildly inflated cost estimates and resistance to seriously considering it.
The Bottom Line: After accounting for even a few of these key factors, the supposed $500 million gap between overhead and underground narrows significantly. Connecticut deserves a reliable, transparent estimate and a future-focused solution—not a profit-driven workaround that seizes land from the very ratepayers UI is meant to serve.
Jim Cole calls this “gold-plating” and “special treatment.” We call it basic accountability.
We fully support strengthening the grid and modernizing our infrastructure—but not at the expense of Connecticut’s communities, property owners, and historic resources, and certainly not when the benefits flow to another state with no obligation to share in the cost.
Fairfield and Bridgeport deserve better. Connecticut deserves better.
Our sincere hope is that UI invites us to the table to develop a solution that works for both the company and the state. United Illuminating has the chance to be a true community partner. We hope they choose to take it.