Glastonbury Paving Begins On Five Roads; Water Main Work Delays Some Final Surfaces

Parts of three roads will receive only a first pavement layer until MDC completes a planned water main installation in 2027.

Glastonbury has begun its final paving work of 2026 on five roads. (Chris Dehnel/Patch)

Glastonbury has begun its final paving work of 2026 on five roads, but portions of three will wait until 2027 for their finished surface, according to the town. The work covers Stonepost Road, Leigh Gate Road, Heather Glen Road, Steep Hollow Road and Ashley Court.

In its Wednesday, Nov. 4, update, the town outlined three to four weeks of pavement reclamation, grading and paving. Once paving is complete, curbing and driveway aprons will be installed and the curb backfilled. Seeding of disturbed areas will follow in spring 2027.

Subscribe

According to the town, MDC plans to install a new water main in the Hopewell Road area during winter and spring 2027. That project overlaps portions of Stonepost Road, Leigh Gate Road and Heather Glen Road. Those sections will receive only their first pavement layer during the current work to avoid cutting into a newly finished surface.

The final pavement surface on the affected sections is planned for summer or fall 2027, after the water main project is complete. Questions about the paving program can be directed to the Town Engineering Division at 860-652-7735.

Source: "Street Paving Program Update / Accommodations for Planned MDC Watermain Installation" (glastonburyct.gov)

Found a problem with this article? Let us know.
More from Glastonbury
News | 21m
News | 16h
News | 21h
See more on Patch >

Sign up for free local newsletters and alerts for the
Glastonbury Patch

Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.

©2026 Patch Media. All Rights Reserved

Do Not Sell My Personal Information