Subcontractors Approved for Schools Project Listed

Thirteen subcontractors will cost $11 million, or $800,000 under the $11.8 million approved at referendum.

The following is a list of the companies that were awarded the bids, their amounts and the work they will perform for the East Granby elementary school project at R.D. Seymour and Allgrove Schools:

Site Construction: Mid-State - $1,091,000
General Trades: Nosal Builders - $1,301,700
Concrete: Waterbury Masonry - $162,989
Roofing: Silktown Roofing - $479,700
Aluminum Windows: Cherry Hill Glass - $351,475
Acoustical Ceilings: Drywall Unlimited - $87,599
Finish Floors: Urban Contractors - $422,456
Painting: Demonte Painting - $56,450
Drywall: Drywall Unlimited - $387,857
Fire Protection: Smith Auto Sprinkler - $105,840
Plumbing: Crest Mechanical - $423,600
Mechanical: HHS Mechanical - $1,638,500
Electrical: Ferguson - $875,000

The total of the bids, plus abatement, soft costs (i.e. architect, owner contingency engineers, etc.), construction manager and construction contingency comes to about $11 million, according to First Selectman Jim Hayden.  

The town allocated $11.8 million at referendum for the project, which is $800,000 under budget after the bidding process. As such, numerous alternates, including the replacement of the playscape at Seymour, installing a dehumidifier in the kitchen at Allgrove, replacing windows, upgrading the electrical systems and renovating the toilet rooms in the classrooms at both schools will also be included in the project.

“It was good news and lots of good stuff,” Hayden said at the Board of Selectmen meeting on Wednesday evening.

No date has been set to begin work on the project, though a groundbreaking ceremony is in the works, according to school officials.