NEW CANAAN, CT — Eversource released the following summer schedule for its natural gas expansion project in New Canaan. All dates are subject to change depending on weather conditions:
- Douglas Road 6/1/18 (start) to 6/10/18 (finish)
- 399 Old Stamford Road (Route 106) to Farm Road 6/7/18 to 6/18/18
- 343 South Avenue (Route 124) to Farm Road 6/7/18 to 6/29/18
- Gower Road 6/11/18 to 6/21/18
- Farm Road 6/19/18 to 6/28/18
- Kelley Green 6/22/18 to 6/29/18
- 558-399 Old Stamford Road (Route 106) 6/29/18 to 7/16/18
- Elm Place 7/2/18 to 7/10/18
- Farm Road to Old Stamford Road (Route 106) 7/2/18 to 7/16/18
- Woodland Road 7/11/18 to 7/20/18
- Oak Street to Main Street 7/17/18 to 8/5/18
Image via Eversource
To sign up for New Canaan breaking news alerts and more, click here.
Find out what's happening in New Canaanfor free with the latest updates from Patch.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.