Soil, Wetlands Complicate Suffield School Building Plans

Planners are reconsidering where a future school could be built after testing found poor soil conditions and three vernal pools.

SUFFIELD, CT — Soil problems, wetlands and vernal pools have complicated Suffield’s plans for a major middle school building project, forcing officials to reconsider where a future school could be placed.

The conditions have limited the portion of the school property considered suitable for construction and delayed the planning process, according to an update presented to the Board of Selectmen.

Testing included five soil borings reaching depths of approximately 38 feet. The eastern portion of the property was found to have less favorable conditions and a greater risk of uneven settlement, according to Permanent Building Commission meeting minutes.

Find out what's happening in Suffieldfor free with the latest updates from Patch.

Building in that area could require structural fill and an extended period of monitoring to allow the ground to settle, potentially delaying construction by about a year.

Conditions were better on the western side of the property, where planners believe a conventional foundation could be used with crushed stone and geotextile material.

Find out what's happening in Suffieldfor free with the latest updates from Patch.

A separate environmental review found several wetlands and three vernal pools. Required setbacks around those areas further reduced the amount of land available for development.

Planners are now looking at shifting the proposed building area toward the western and southern portions of the campus. Preparing a relocated building pad could add approximately $500,000 to the project.

The Permanent Building Commission has also discussed using a more compact building design, reducing parking where possible and relocating athletic facilities, including the tennis courts. Acquiring neighboring property was considered, but no action was taken.

Town officials are now working on another campus layout that could avoid purchasing additional land while improving bus and vehicle circulation. The revised plan must also account for parking, athletic fields, stormwater drainage and wetland setbacks.

The town is still considering both renovation and new-construction options for the middle school. Updated cost estimates will be prepared once a preferred layout is developed.

Suffield Middle School, located at 350 Mountain Road, was built in the early 1960s. The town has identified major needs involving its heating and cooling systems, roof, electrical infrastructure, accessibility and overall layout.

Officials previously hoped to have a project ready for an early March referendum. The planning process is now expected to continue into the spring, although Dec. 1 remains a target for establishing the overall budget and preparing information for bond counsel, according to Board of Selectmen minutes.

For more Northern Connecticut news, follow Patch editor Jay Kenney.