Willow Bend Parkway Paving To Begin Monday
The Willow Bend Parkway Pavement Rehabilitation Project is scheduled to begin the week of Sept. 9.

LAND O' LAKES, FL — The Willow Bend Parkway Pavement Rehabilitation Project is scheduled to begin the week of Sept. 9.
The paving project includes both the eastbound and westbound lanes of Willow Bend Parkway from Land O’ Lakes Boulevard to Collier Parkway. The road work will include milling and resurfacing the existing roads, as well as new pavement markings and re-striping.
Work will take place Sunday through Thursay from 7 p.m. to 7 a.m.
Find out what's happening in New Port Richeyfor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
Expect single lane closures with message boards directing traffic. The target completion date is Sept. 30, depending on weather conditions
Ajax Paving Industries of Florida LLC is the contractor for this Pasco County Public Works Department project.