Etowah River Bridge Works Starts Monday
Traffic will be reduced to one lane in each direction along U.S. 411/S.R. 20 at the bridge near the Bartow-Floyd county line.

BARTOW COUNTY, GA -- The Georgia Department of Transportation is advising motorists on U.S. 411/S.R. 20 in Bartow and Floyd counties that work on the bridge over the Etowah River will resume immediately following the Thanksgiving holiday.
Starting Monday, Nov. 28, the Georgia DOT contractor will begin to work on the rehabilitation of this bridge. Traffic will be reduced to one lane in each direction.
Work on the bridge over Etowah River is part of a maintenance project to rehabilitate several bridges at various locations in Bartow and Floyd counties.
Find out what's happening in Cartersvillefor free with the latest updates from Patch.
Bridge rehabilitation work includes deck replacement, resetting bearings, application of polymer overlays, epoxy injection of the substructure members, joint replacement, correction of spalls in substructure, repair of undermining at the abutments, bridge deck rehab utilizing a modified latex overlay (and painting of structural steel.
Work on this project, which costs a little more than $6 million, started earlier this month, and is scheduled to be completed by the end of March 2017.
Find out what's happening in Cartersvillefor free with the latest updates from Patch.
“We certainly hope that all motorists watch out for any change in traffic pattern and be extra cautious while approaching this work zone,” said DeWayne Comer, district engineer at the DOT office in Cartersville. “This project may be causing the public some inconvenience, but upon completion, it will improve the flow of traffic on U.S. 411, make it safer, and help the public get where they need to go in Bartow and Floyd counties."
Image via Patch
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.