Water System Improvements To Begin in Dacula Area

The project is scheduled to run into March, 2016.

-------

Work on a the first phase of a water system improvement project in the Dacula area by the Gwinnett Department of Water Resources was scheduled to begin this week, according to a posting on the city’s website.

Find out what's happening in Daculafor free with the latest updates from Patch.

The project could result in traffic delays, especially for residents living along Sanjo Street and Tanner Road.

The work is expected to run into March, 2016.

Find out what's happening in Daculafor free with the latest updates from Patch.

Here are “critical dates” in the project, according to the city:

  • 4/22/15 Notice to proceed, begin clearing ROW
  • 4/23/15 Bore Under Colonial Pipeline
  • 4/30/15 Bore Under W. Drowing Creek RD @ Tanner RD
  • 4/30/15 Bore Tanner RD @ Majestic Cir (S)
  • 5/4/15 Bore Tanner RD @ Michelle Cir
  • 5/7/15 Bore Tanner RD @ Majestic Cir (N)
  • 5/7/15 Exc/Lay/Bfill Sta 106+01 to 84+47
  • 5/12/15 Bore Mobley Dr
  • 5/15/15 Bore Laura Ln
  • 5/20/15 Bore Eastside Dr
  • 5/21/15 Exc/Lay/Bfill Sta 84+47 to 43+75
  • 5/25/15 Bore Tanner Rd @ Spring St
  • 5/28/15 Bore Tanner Rd @ Dacula Cove Dr
  • 6/2/15 Bore Tanner Rd @ Sta 23+00
  • 6/5/15 Bore Tanner Rd @ Franklin Dr
  • 6/18/15 Exc/Lay/Bfill 43+75 to 18+75
  • 7/7/15 Exc/Lay/Bfill 18+75 to 14+00
  • 7/14/15 Exc/Lay/Bfill 13+00 to 13+00
  • 8/4/15 Pressure Test/Disinfect
  • 8/11/15 Tie-in side streets
  • 8/11/15 Pave SanJo St
  • 8/25/15 Swap over meters and services
  • 9/1/15 Restoration
  • 3/22/16 Project Substantially complete
  • 4/23/16 Project final completion

If you have any questions on the project, the project manager is Michael Efeyini — (O) 678-376-7069 and (M) 404-401-8891 or michael.efeyini@gwinnettcounty.com.