Village Approves $14,000 Change Order for West Parking Lot Project

The change order covers costs to clean up the second soil contamination and extra working hours in Libertyville.

Village trustees approved a change order of $14,413 to cover costs for cleaning up the second soil contamination and additional work in the lot behind  and Milwaukee Avenue.

Aldridge Electric, which has been working relocating utilities in Libertyville's west parking lot, .

The soil had to be disposed of in an environmentally correct manner, resulting in additional work for Aldridge Electric that was not part of .

Find out what's happening in Libertyvillefor free with the latest updates from Patch.

The change order also covers:

  • Two additional hand-hole structures that were added to accommodate existing underground conduit that varied from the plans;
  • Time working around two unforeseen concrete structures;
  • Repair of a broken water service line.

Tax increment financing district funds will be used to cover the change order.

Find out what's happening in Libertyvillefor free with the latest updates from Patch.

Mayor Terry Weppler recused himself from the vote because he owns property in the TIF district.

For more about the west parking lot project read:

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.