Rustcraft Rd Sewer Improvements Project In Dedham - Work Schedule For Week Of August 31

Police details will be present to direct traffic around the work area.

August 29, 2020

To date, RJV has installed approximately 3,400 LF (approx 70% of the total 4,885 LF to be installed) of the 10" Ductile Iron Force Main.

Find out what's happening in Dedhamfor free with the latest updates from Patch.

For the week of August 31st, RJV Construction Corp. (Contractor) will be performing the following activities:

  • Excavation for and installation of the 10" force main continuing near Station 15+00 to Station 10+00.

Police details will be present to direct traffic around the work area.

Find out what's happening in Dedhamfor free with the latest updates from Patch.

For up-to-date information and photos regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.

You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.


This press release was produced by the Town of Dedham. The views expressed here are the author’s own.