Community Corner

Rustcraft Rd Sewer Improvements Project In Dedham - Work Schedule For Week Of July 20

Police details will be present to direct traffic around the work area.

July 17, 2020

For the week of July 20th, RJV Construction Corp. (Contractor) will performing the following activities:

Find out what's happening in Dedhamfor free with the latest updates from Patch.

  • Excavation for and installation of the 10" force main continuing near Station 36+00 (Near concession stand at Fairbanks Field) to Station 30+00 (About 300 feet South of the Batting Cage at Fairbanks Field)

Police details will be present to direct traffic around the work area.

For up-to-date information and photos regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.

Find out what's happening in Dedhamfor free with the latest updates from Patch.

You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.


This press release was produced by the Town of Dedham. The views expressed here are the author’s own.