RJV will continue repaving work along Rustcraft Road. There may be delays as police manage traffic through this area.
October 9, 2020
To date, RJV has installed approximately 4,800 LF (approx 98% of the total 4,885 LF to be installed) of the 10" Ductile Iron Force Main.
Find out what's happening in Dedhamfor free with the latest updates from Patch.
For the week of October 12th, RJV Construction Corp. (Contractor) will be performing the following activities:
- Excavation for and installation of the 10" force main continuing near Station 1+00 to Station 0+00.
- RJV will be off of Rustcraft Road after Station 8+00. Work occurring from Station 8+00 to the Pump Station will occur within the Town's Sewer Easement that runs through AvalonBay's property.
- RJV will continue repaving work along Rustcraft Road. There may be delays as police manage traffic through this area.
Police details will be present to direct traffic around the work area.
Find out what's happening in Dedhamfor free with the latest updates from Patch.
For up-to-date information and photos regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.
You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.
This press release was produced by the Town of Dedham. The views expressed here are the author’s own.