Rustcraft Rd Sewer Improvements Project - Work Schedule For Week Of June 15
Construction will be starting on June 22 near the intersection of Central Avenue and Rustcraft Road.
June 12, 2020
For the week of June 15th, RJV Construction Corp. (Contractor) will performing the following activities:
Find out what's happening in Dedhamfor free with the latest updates from Patch.
- Laying out the piping for the project along the shoulder and off the roadway along Rustcraft Road.
- Conducting test pits at various locations along the force main alignment to verify existing utility locations where the proposed force main comes within close vicinity to other existing utilities.
Construction will be starting on Monday 6/22 near the intersection of Central Avenue and Rustcraft Road. Dedham police details will be present to direct traffic around the work area.
For up-to-date information regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.