06/25/2021 4:54 PM
Eversource Gas:
Find out what's happening in Dedhamfor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
- Lincoln Street; The gas main is installed. Eversource will be removing old valve boxes.
- Adams Street: No work at this time. The remaining work will be after Elmwood Ave is complete.
- Elmwood Ave: Work continues from Adams to Jefferson. This work will continue thru July.
- Court Street Washington ST Wilson Ave construction. This wok is continuing on Washington St and continuing towards Richards Street.
Sprague Street Sidewalk Construction:
- Limits of work are from Cedar St to Greenlodge St and Cedar St to Dresser Ave
- The sidewalk work will be completed the week of July 25th
Rustcraft Rd Project
Find out what's happening in Dedhamfor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
- Eversource Electric has installed the majority of the conduit.
- They will be onsite working on installing manholes and handholes
- RM Pacella will be doing tree work including trimming and clearing.
- Expect traffic delays
Bridge and Ames Street Reconstruction
- Curbing and Sidewalk work will begin.
- The contractor will begin near Bingham Ave and will work towards Moseley's
- Utility Companies will continue to transfer their wires
- If you have any issues with the construction on Bridge Street please contact Northern Construction The Contact is Graham Johnson:
- Office: (413) 289-1230 x209
Eastern Ave - Complete Streets
- The Drainage work will continue at various locations.
- If possible the Dedham Police will try to maintain two way traffic thru one lane.
- Expect Delays
Eastern Ave - Water Project
- The water main is complete.
- The contractor will be working on service connections.
Pine Street
- The water main has been installed.
- Water Services will be installed in mid July.
Schiller Rd and Ridge Ave
- Revoli Construction will be installing services on both streets.
- Water Services will be installed thru July 12
If anyone has any questions on these projects please contact the DPW at 781-751-9350 or Jflanagan@dedham-ma.gov
This press release was produced by the Town of Dedham. The views expressed here are the author’s own.