For the week of July 6th, RJV Construction Corp. (Contractor) will performing the following activities:
Find out what's happening in Dedhamfor free with the latest updates from Patch.
- Excavation for and installation of the 10" force main continuing near Station 42+50 (Near Central Avenue) to Station 37+00 (Near concession stand at Fairbanks Field)
Police details will be present to direct traffic around the work area.
For up-to-date information regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.
Find out what's happening in Dedhamfor free with the latest updates from Patch.
You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.
This press release was produced by the Town of Dedham. The views expressed here are the author’s own.