This post was contributed by a community member. The views expressed here are the author's own.

Neighbor News

KEMA Inc Ecology and Environment Wind Turbine Special Permit

April 19,2005 Page 28 of the April 19, 2005 site review says : 6.2.2 a special permit is needed for the wind turbi

The big question is why wasn’t a Special Permit pulled to build the Wind 1 turbine ?

A study was completed on April 19,2005 and said a Special Permit is required.

Timeline:
The Falmouth Energy Committee minutes and discussed in the 3/28/2005 minutes .

Find out what's happening in Falmouthfor free with the latest updates from Patch.

The rough draft of the Falmouth Community Wind Project Site Screening Report was reviewed at this meeting with all the members of the Falmouth Energy Committee and the Falmouth Select Board .

Next : The feasibility study was done for Falmouth in two parts one April 19,2005 and November 2005 .

Find out what's happening in Falmouthfor free with the latest updates from Patch.

The first part of the study is not on the town web site or the CBI documents for some unknown reason.

The April 19 ,2005 report clearly shows that a review of the Cape Cod Commission etc shows a SPECIAL PERMIT is required.

Falmouth Community Wind Project Site Screening Report Apr 19, 2005 – FALMOUTH SITE SCREENING REPORT

This report was prepared by KEMA ECOLOGY AND ENVIRONMENT, INC and funded by the Massachusetts Technology Collaborative.

The date of the report April 19, 2005

The report says a Special permit is needed .

Falmouth Wind 1 Turbine Falmouth Community Wind Project Site Screening Report April 19,2005



The date is important for this report April 19,2005 Page 28 of the April 19, 2005 site review says : 6.2.2 a special permit is needed for the wind turbi

The views expressed in this post are the author's own. Want to post on Patch?