Wakefield Publishes National Grid Construction Update For Week Of September 15
Construction crews plan to extend their work at certain work sites through close of business on September 19.
September 15, 2020
Have you signed up for National Grid’s Wakefield-to-Woburn Line update email? Their weekly overview provides project progress and related traffic-management information. View the project page and sign up to receive it in your inbox.
Find out what's happening in Wakefieldfor free with the latest updates from Patch.
Among the updates National Grid notes this week:
- Crews have completed 50 percent of the duct bank installation for the project in Wakefield.
- Water Street: Crews continue excavation and duct bank installation near the intersection of Water Street and Vernon Street.
- Two-way traffic facilitated by a police detail.
- Broadway: National Grid contractors are working with the Wakefield Municipal Gas and Light Department near the Foundry Street intersection.
- Through-traffic will be restricted to residential, business-related, and emergency traffic.
- Businesses within the closure area will remain open during construction.
- Montrose Avenue: Excavation and duct-bank installation continues.
- No through-traffic during work hous; emergency and residential vehicle access only.
- Construction crews plan to extend their work at certain work sites through close of business on Saturday, September 19.
Contact
Find out what's happening in Wakefieldfor free with the latest updates from Patch.
If you have questions about current or upcoming work, you can contact a member of the National Grid project outreach team by emailing info@ma-nhsolution.com or calling 1-844-646-8427.
This press release was produced by the Town of Wakefield. The views expressed here are the author’s own.