The direction of Town House Road is anticipated to be reversed while work is in the area of the Church Street intersection.

April 24, 2020

Town Center Paving Work Continues

  • Binder pavement from Center St to School St is anticipated to occur on Saturday, April 25th and is anticipated to continue to the 28th
  • The work day to install both base and binder pavement will start early, 6:00 a.m. +/-, due to the process and access through intersections
  • The direction of Town House Road is anticipated to be reversed while work is in the area of the Church Street intersection. Detours will be employed.

Please visit the project web page for additional details.

Find out what's happening in Westonfor free with the latest updates from Patch.

General visual depictions of the upcoming surface work can be found on the Project Summary and Project Views web pages. This also includes the historical context of the Town Green District.

Weston.org/TownCenter