Caldwell Road Repaving Program For 2020-2021

Caldwell has released a list of streets due to be repaved during the construction season of 2020 and 2021.

May 7, 2020

Road Repaving Program 2020-21

Find out what's happening in Caldwellsfor free with the latest updates from Patch.

The following street are scheduled for repaving during the construction seasons of 2020 and 2021.

The Borough's practice with repaving is to first complete all necessary repairs to the infrastructure located in the roadway, which includes water pipes, sewer pipes and electric and gas utilities, prior to doing the work on the road surface. As a result, you may experience excavation and underground construction on these streets prior to the road work taking place.

Find out what's happening in Caldwellsfor free with the latest updates from Patch.

The Borough will notify all residents in advance of any infrastructure work and will make arrangements to provide access to all properties during the construction period. Thank you in advance for your understanding and cooperation during this process.

Caldwell2020-21 Road Program

Street From To

Water Project A

Birkendene All

Leacroft All

Prospect All

Thomas All

Westville Thomas End of Cemetery

Westville Cherry Birkendene

Water Project B

Hatfield Street Forest Smull

Forest Avenue All

Crane Arlington Erwin

Water Project C

Central Aveneue Miller Wakefield

Welshman Court All

Ella All

Miller All

Prior Water Projects

Central Place All

Kirkwood All

Francis All

Overlook Jackson Cedars

Streets (Condition Based)

Hilllside All

Crane (w Storm Sewer) Arlington Forest

Harrison All

Westover All

Ryerson All

Ashland All

Personnette All

Ravine All

Cleveland Road All

Bowers/Cherry Lane Cherry Hanlon


20-21 Road Program