$368K Awarded To Complete Amsterdam Drive In Hillsborough
The NJDOT awarded Hillsborough a grant for $368,400 for repaving the final phase of Amsterdam Drive. See the timeline of completion:
HILLSBOROUGH, NJ — The final and third phase of the Amsterdam Drive project has received funding, said Hillsborough Committeeman John Ciccarelli at the Tuesday meeting.
The New Jersey Department of Transportation awarded a Local Aid grant to the township for $368,400 for the repaving of Amsterdam Drive.
"The township received grants for all three phases so full repaving will be at a minimal cost to the township," said Ciccarelli.
Find out what's happening in Hillsboroughfor free with the latest updates from Patch.
The first phase of the project which included portions of the roadway between Millstone River Road and Vliet Drive was completed in 2022. Read More: Amsterdam Drive Repaving Project To Begin As Weather Warms Up
The second phase, which includes Amsterdam Drive between Vliet Drive and Murphy Drive, will begin this coming spring, said Ciccarelli.
Find out what's happening in Hillsboroughfor free with the latest updates from Patch.
The final and third phase still needs to be designed and approved by NJDOT before it can go out to bid.
Ciccarelli anticipates work to begin on the final phase, which includes the roadway between Murphy Drive and Amwell Road, in 2024.