WEST WINDSOR, NJ — Repairs to the Clarksville Road Bridge are moving forward, with crews working through rainy weather and the weekend, according to a Monday update from Mayor Hemant Marathe.
Marathe said the New Jersey Department of Transportation worked every day last week, including Thursday night and both weekend days.
"I am happy to note that NJ DOT worked every day last week on the Clarksville Road Bridge restoration," Marathe said.
The township continues requesting longer track outages from Amtrak to help accelerate repairs.
Jesus Alcazar, director of NJDOT, said the department is coordinating necessary utility relocations with Amtrak, PSE&G, West Windsor Township and other project partners.
Meanwhile, the project's designer is reviewing comments from Mercer County and West Windsor Township for a traffic analysis memorandum.
As Patch previously reported, crews were fabricating structural steel in August while officials worked to resolve utility issues and secure traffic-signal approvals, with no confirmed reopening date.
In a November follow-up, Patch reported that NJDOT began bridge deck repairs Oct. 20, as the closure reached the one-year mark and township officials demanded action over prolonged detours affecting more than 15,000 vehicles daily.
Residents can follow additional updates on the township's bridge information page.
Have a correction or news tip? Email dani.sepe@patch.com.
Sign up for free local newsletters and alerts for the
West Windsor Patch
Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.