Referendum Work Advances, 3 Construction Contracts Awarded In Westfield
Foundation work is expected within two weeks as Westfield moves ahead with school referendum projects at three schools.

WESTFIELD, NJ — Westfield's school referendum construction moved ahead as the Board of Education reviewed the project timeline and approved contract awards for work at Washington, Wilson and Franklin elementary schools.
On Tuesday, the Board of Education voted to approve three contract awards for Franklin Elementary, Washington Elementary, and Wilson Elementary schools.
"Bid participation has been strong and bids received so far are within budget," said Board member Kent Diamond.
Find out what's happening in Westfieldfor free with the latest updates from Patch.
The board's resolution on Washington Elementary School denied a bid protest from Grove Contracting LLC and awarded the contract to Delric Construction Co., Inc. of North Haledon for $15,278,000. The resolution states that 13 bids were received.
According to the resolution, Grove protested the proposed award to Delric, contending Delric's bid was non-responsive because it did not submit a price for "Alternate No. 1 – Epoxy Terrazzo Flooring."
Find out what's happening in Westfieldfor free with the latest updates from Patch.
The board found that the bid form contained no line or space for pricing any alternate, that the bid documents did not include a specification for epoxy terrazzo flooring, and that Delric's bid conformed in all material respects to the bid documents. The resolution states that Alternate No. 1 is not included in the award or the contract.
For Wilson Elementary School, the board awarded the alterations project to Shorelands Construction, Inc. of Long Branch for $6,999,000, inclusive of allowances. The resolution states that six bids were received.
For Franklin Elementary School, the board awarded the additions and alterations project to Brockwell & Carrington Contractors, Inc. of Towaco for $17,727,500, consisting of a base bid of $17,592,500 and Alternate No. 1 of $135,000 for epoxy terrazzo flooring throughout the hallways and stairs of the addition. The resolution states that nine bids were received.
Diamond also noted that at McKinley Elementary School, "the contractor has mobilized. Deliveries are arriving and foundation work is expected to begin within the next two weeks."
He also said the district had its groundbreaking photo last week.
"All kindergarten construction projects are currently projected to begin before the end of this school year," said Diamond. "The next three summers will be critical to the referendum schedule."
According to Diamond, the target for elementary school completion remains September 2028, and "as of today, we are still on schedule for kindergarten to open in September of 2028."
Diamond said portions of the intermediate and high school projects are expected to continue during the summers of 2028 and 2029, and that progress will be reviewed monthly.
He said the approved 2027-28 and 2028-29 school calendars maximize the summer construction window, and that the board will revisit holiday closure considerations in future calendars once construction is complete.
Have a news tip? Email alexis.tarrazi@patch.com.