Road Paving Program Starts In Warminster
Warminster Township will begin paving five miles of roads starting on Monday. That is one week ahead of originally planned.
WARMINSTER, PA —The township's 2024 Road Program is scheduled to begin on Monday, one week earlier than originally planned, officials said,
Township officials said that a contractor is filming conditions of the designated roadways this week for a preconstruction video.
The road paving project is expected to be completed within 90 days. The program includes the resurfacing of about 5 miles of roadway.
Find out what's happening in Warminsterfor free with the latest updates from Patch.
At a recent meeting, Warminster Township Supervisor Chairwoman Katherine Frescatore said that the township was known as "Pothole City" but that officials have worked hard to pave over that image.
These are the roads planned for repaving under the township's 2024 Road Paving Project:
Find out what's happening in Warminsterfor free with the latest updates from Patch.
- Ivyland Road —Mearns Road to Ivyland Borough
- Thomas Drive —Ivyland Road to Cul-De-Sac
- Mueller Road — Stratford Road to End
- Harting Circle —Phillips Road to Cul-De-Sac
- Brook Lane —Phillips Road to End
- Hallowell Avenue —Phillips Road to End
- Mason Drive —Hallowell Avenue to Orchard Avenue
- Orchard Avenue —Mearns Road to End
- Phillips Road —Orchard Avenue to 379 S. Norristown Rd.
- Louis Drive —Ivyland Road to Street Road
- Constance Drive —Louis Drive to Nina Way
- Mary Street —Street Road to End
- Catherine Street —Street Road to End
- S. Norristown Road —County Line Road to Street Road