North Nashville Bikeway Progress Update
The following are some high points of North Nashville Bikeway Progress.
Posted 1/21/2020
North Nashville Bikeway Progress Update
The following are some high points of North Nashville Bikeway Progress:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
Work accomplished January 13 through 17, 2020
- Delineators on Arthur Ave completed.
- Striping on Arthur Ave completed (except for corrective work).
- Striping on Buchanan St & Garfield St continued.
- Bike symbols and arrows installed from 3rd Ave N to 9th Ave N.
- Buffer lines installed from Rosa L Parks to 9th Ave N.
- Parking lines/edge lines installed from Rosa L Parks to Delta Ave.
- Signs completed on Ed Temple Blvd.
- Final pedestrian pole footings on Buchanan/Garfield completed.
Two-Week look ahead:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
- Delineator installation on Ed Temple Blvd.
- Striping to continue on Buchanan St/Garfield St and on Ed Temple at Jefferson St as weather allows (minimum temperature of 50 degrees and dry conditions)
- Complete sign installation on Arthur Ave
- Corrective concrete work on DB Todd Blvd at Wheless St.
- Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave.
This press release was produced by the City of Nashville. The views expressed here are the author’s own.