North Nashville Bikeway Progress Update
The following are some high points of North Nashville Bikeway Progress from the Project Manager.
Posted 1/31/2020
Find out what's happening in Nashvillefor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
The following are some high points of North Nashville Bikeway Progress from the Project Manager:
Updates for January 27 through 31, 2020:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
- No striping installed this week.
- Delineator installation completed on Ed Temple between Jefferson St and Buchanan St.
- Corrective work on curb ramp on DB Todd at Wheless completed.
- Met with Stansell to look at intersection work on DB Todd at both Jo Johnston and Jefferson St.
- Laid out the new pedestrial pole location and called in for TN ONE CALL and determined the limits of concrete work.
- Communications ongoing with Google regarding concrete work at DB Todd & Underwood. They came back with a 90 day relocation schedule. We responded that it needs to be done sooner than that and they are working on expediting their schedule.
Two-Week look ahead:
- Striping to continue on Buchanan St/Garfield St and on Ed Temple at Jefferson St as weather allows (minimum temperature of 50 degrees and dry conditions).
- Complete sign installation on Arthur Ave.
- Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave.
- Continue Google communications for relocation at DB Todd & Underwood.
- Lay out excavations for islands and curb work on Monroe to see if there are any Google conflicts.
Contact: TransportationPlanner@nashville.gov
This press release was produced by the City of Nashville. The views expressed here are the author’s own.