North Nashville Bikeway Progress Update
The DB Todd southbound bike lane work can begin Sept. 2.
August 24, 2020
The following are some high points of North Nashville Bikeway Progress:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
Work accomplished 8/8/20 - 8/14/20:
- Marking Impressions continued thermoplastic installation on DB Todd. The fiber installation on DB Todd is impacting the ability to work in the southbound bike lane. The Metro Permits Office has set a September 1, 2020 deadline for the fiber contractor to have their work complete in the bike lane. If they are not complete by then, the NNB project can move ahead and it will be the fiber company’s responsibility to repair any damaged bikeway striping.
- HA5 Fog Seal warranty work completed.
- Marking Impressions has began permanent striping on the HA5 portion of Ed Temple and all long line is complete.
- Marking Impressions installed the LOADING ZONE legend on Arthur.
Two-Week look ahead:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
- Marking Impressions to continue new pattern install on DB Todd. The DB Todd southbound bike lane work can begin September 2, 2020.
- Marking Impressions to begin detail work on Ed Temple HA5 section.
- Marking Impressions to install the additional dotted line on Arthur.
- PRI to continue MMA installation on Buchanan / Garfield and stencil work on Ed Temple and Arthur.
- Resolve sign issue for pedestrian sign at Scovel and install sign.
- Coordination with Google Fiber for relocation work on Monroe St.
Concrete repair by NES where pole was removed at DB Todd & Jo Johnston intersection.
This press release was produced by the City of Nashville. The views expressed here are the author’s own.