North Nashville Bikeway Progress Update
Work for the next two weeks, weather permitting, has been announced.
January 19, 2021
Two-Week look ahead as weather allows:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
- Vulcan to begin delineator installation on DB Todd and install pedestrian sign at Scovel.
- Marking Impressions to install snowplowable markers on DB Todd.
- PRI to continue white MMA stencil work on Ed Temple, Arthur, Buchanan / Garfield, and DB Todd and install green
- MMA on DB Todd in areas that had been held up due to fiber work – as weather allows.