The following are some high points of North Nashville Bikeway Progress from the Project Manager:
Work accomplished January 10 – January 14, 2020
Find out what's happening in Nashvillefor free with the latest updates from Patch.
By subscribing, you agree to Patch's Privacy Policy and Terms of Use.
- The weather did not cooperate this week at all, again, either rain, wet, or temperature.
- Demolition began for the concrete work on Buchanan St at 14th Ave N, and Buchanan St at 11th Ave N/Arthur St.
- Communications ongoing with Google regarding concrete work at DB Todd & Underwood.
Two-week look ahead:
- Striping to continue on Buchanan St/Garfield St and on Ed Temple from Jefferson St to Buchanan as weather allows (minimum temperature of 50 degrees and dry conditions).
- Complete sign installation on Arthur Ave. once equipment is repaired.
- Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave. to continue.
- Continue Google communications for relocation at DB Todd & Underwood.
This press release was produced by the City of Nashville. The views expressed here are the author’s own.