North Nashville Bikeway Progress Update

Striping work is planned to continue on Buchanan and Garfield and may complete next week.

May 13, 2020

The following are some high points of North Nashville Bikeway Progress:

Find out what's happening in Nashvillefor free with the latest updates from Patch.

Work accomplished 5/2/20 – 5/8/20:

  • Marking Impressions continued work on Buchanan and Garfield.
  • Detectable warnings installed as specified in plans on Buchanan, Garfield, and DB Todd.
  • Tuff Curbs on Arthur completed.
  • Permanent Signs installed on Buchanan & Garfield.
  • PRI placed topsoil behind concrete work on DB Todd at Underwood and Wheless.
  • Stansell completed prep work for ped signals on Buchanan and Garfield.

Two-Week look ahead:

Find out what's happening in Nashvillefor free with the latest updates from Patch.

  • Striping work is planned to continue on Buchanan and Garfield and may complete next week.
  • Stansell to set ped poles on Ed Temple, Buchanan, and Garfield.
  • Vulcan to install delineators on Buchanan / Garfield.
  • Stansell to excavate and pour ped pole footing on DB Todd at Jo Johnston.
  • PRI to place sod behind concrete work on DB Todd at Underwood and Wheless.
  • Marking Impressions to lay out new pattern on DB Todd and then begin line removal and new pattern install.
  • Coordination with Google Fiber for relocation work on Monroe St.