North Nashville Bikeway Progress Update
Stansell completed installation of ped poles and rapid flashers on Ed Temple, Buchanan, and Garfield.
May 18, 2020
The following are some high points of North Nashville Bikeway Progress:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
Work accomplished 5/9/20 – 5/15/20:
- Marking Impressions continued work on Buchanan and Garfield and its down to striping on I-65 bridge and double yellow between Rosa Parks and 3rd Ave N.
- Stansell completed installation of ped poles and rapid flashers on Ed Temple, Buchanan, and Garfield.
- Permanent pedestrian signs completed on Buchanan & Garfield.
- NES removed abandoned pole at DB Todd and Jo Johnston intersection, but it still needs concrete repair by NES.
- Marking Impressions began lay out of new pattern on DB Todd.
Two-Week look ahead:
Find out what's happening in Nashvillefor free with the latest updates from Patch.
- Striping work is planned to continue on Buchanan and Garfield and should complete next week.
- Marking Impressions to install snowplowable markers on Buchanan & Garfield.
- Marking Impressions to continue lay out of new pattern on DB Todd and then begin line removal and new pattern install.
- PRI to place sod behind concrete work on DB Todd at Underwood and Wheless.
- Vulcan to install delineators on Buchanan / Garfield.
- Stansell to excavate and pour ped pole footing on DB Todd at Jo Johnston.
- Coordination with Google Fiber for relocation work on Monroe St.
This press release was produced by the City of Nashville. The views expressed here are the author’s own.