Old Bridge Road Update from Supervisor Mike May
My most recent E-Update regarding some important changes along the Old Bridge Corridor.

Greetings!
We've sent out quite a few E-Updates recently but I thought it was important to alert you to some important changes you may have noticed along the Old Bridge Corridor. I hope you will take the time to read this information and pass it along to your friends and family.
Old Bridge Road UpdateOver the past few days, I have received numerous inquiries as to the construction along Old Bridge Road. As you drive along the road, you too may have noticed the jersey barriers, heavy equipment, barrels, cones and other indications of construction activity from about Oakwood Drive all the way down to Rolling Brook Drive. This is part of a series of safety improvements to the corridor, including improving sight distance, upgrading various intersections, modifying "superelevation," and enhancing pedestrian facilities (however, no widening of Old Bridge will occur).
Find out what's happening in Lake Ridge-Occoquanfor free with the latest updates from Patch.
When completed, these projects should improve safety and promote better traffic flow along Old Bridge. However, in the meantime, you will see construction equipment and activity and it will have some impact on travel conditions from time to time. In fact, about two weeks ago on Friday afternoon at about 5:00 p.m., my office received a phone call from a concerned constituent who mentioned that VDOT had forgotten to remove the barriers from the construction project between Rolling Brook and Harbor before rush hour began. As a result, we alerted the county police and officers were immediately dispatched to move the barriers in order to increase the flow of traffic. Unfortunately, as many of you commuting that day probably realized, the traffic situation had already become a disaster.
Following the incident, we have been working with VDOT to understand what occurred that day and try to prevent it from happening again. As it turns out, the traffic barriers were left in place intentionally as VDOT considered a permanent lane closure as part of its ongoing improvements. This would have left one westbound lane closed for several weeks, including during rush hour.
Find out what's happening in Lake Ridge-Occoquanfor free with the latest updates from Patch.
Obviously, this was very concerning. Construction normally occurs between the hours of about 9 a.m. and 3 p.m. so as to avoid major impacts on the morning and afternoon commuters. As a commuter on Old Bridge myself, I realize that we simply cannot shut this much of a lane down during rush hour--particularly if the closure is going to last for weeks. The good news is that VDOT has re-evaluated their plans following meetings with my office and our county transportation staff. Although the new plan will still have some impact, itis much more "commuter friendly" and will take effect beginning this Wednesday, September 26.
Specifically, as you drive along Old Bridge, you can expect to see the following changes:
- Eastbound Old Bridge Rd. Concrete barriers along the left side of the road will remain in place until approximately April of 2013. No lanes have been taken away.
- Westbound Old Bridge Rd. The right lane at Minnieville Road will be limited to right turns only. Measures to direct traffic shift and communicate changes include revised pavement markings, signage and Variable Message Signs. This traffic pattern will remain in place until approximately April of 2013. Two through lanes and left turn lanes at Minnieville and Harbor Road (modified) will remain.
I understand that this is still not the ideal situation; however, it is certainly preferable to the original proposal. My staff and I will monitor the progress of this project and work closely with VDOT over the course of the next several months to make sure that any other issues that may arise are resolved as quickly as possible. We will certainly continue to keep you apprised of any new information as it becomes available. I do not anticipate this will cause major delays and once people get used to the modified traffic pattern, it should be okay. However, in the meantime, you may want to consider the Prince William Parkway as an alternative to Old Bridge in the afternoons if it suits your commuting needs.
As mentioned above, the construction is part of a series of improvements to the Old Bridge Corridor. To that end, below is a table that VDOT has produced, which provides more detail on each project. It will give you an idea as to what to expect in the next few years (including what has been completed and what remains to be completed). Please feel free to pass this information along to other commuters who may not be signed up to receive our E Updates.
Old Bridge Corridor Projects (as of Sept. 2012)
Description
Status
Improve signal visibility and upgrade traffic signal at Elysian Dr.
Project was advertised for Construction in Spring 2012. Construction has been completed.
Upgrade traffic signal, improve signal visibility and provide pedestrian accommodations at Clipper Drive.
Project was advertised for Construction in Summer 2012. Construction to proceed in 2012.
Upgrade traffic signal at Occoquan Road.
Project was advertised for Construction in July 2012. Construction is nearly completed.
Install Signal Display for EB and WB approaches, Relocate Bus Stop Sign, provide ADA Ramp and sidewalk to Bus Stop, and provide Guardrail End Treatment at Antietam Road
Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).
Extend Left Turn Lane, Upgrade existing traffic signal to Mast Arm and Install Pedestrian Crossings at Springwoods Drive.
Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014.
Upgrade existing Signal and install Pedestrian Crossings with ADA Ramps at Hedges Run Drive (design is being coordinated with County Sidewalk/ Superelevation project).
Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).
Upgrade Existing Traffic Signal and convert span wire signal support to mast arm mounts at Westridge drive.
Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).
Upgrade Signal to Mast Arm Design, Install Ped. Crossings w. ADA Ramps; Construct/ Offset WB Left Turn Lane on Old Bridge Road at Mohican Drive (design is being coordinated with County Sidewalk/ Superelevation project).
Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014.
Upgrade existing traffic signal from Span Wire to Mast Arm at Smoketown Rd.
Project is currently under Design Phase. Construction advertisement is scheduled for mid 2014 (looking to accelerate under regional signal contract).
Construct sidewalk and improve the cross section to provide moresuperelevation on north side of Old Bridge Road, from Hedges Run to Dillingham Square/Cricket Lane
VDOT Safety project was combined with County sidewalk project for improved coordination and accelerated construction. Project scheduled to be advertised for construction fall 2012.
Offset left turn lanes to improve sight distance and signal visibility at Harbor Drive.
Project was advertised for construction in Spring 2012. Construction has started and is scheduled to be completed in spring 2013.
Reduce run-off-road accidents by adding superelevation and modifying adverse crown on the westbound lanes and
Vertical Alignment Improvements
at Colby Drive
Project was advertised for construction in Spring 2012. Construction has started and is scheduled to be completed in late 2012.
Construct sidewalk, handicap ramps, crosswalks, and install pedestrian signals at specific intersections from Titania to Cricket Lane
Project was advertised for construction in October 2011. Construction has been completed.
Thanks for reading our E-Update! If you would like to receive these E-Updates directly to your email, please contact Alyssa at aedson@pwcgov.org or call 703-792-5180. As always, if we can ever be of service to you, please do not hesitate to contact us by email, phone, or Facebook.
Best regards,
Mike May, Occoquan District Supervisor