Pavement 4-20 Doty Street Reconstruction
April 1, 2020
| Contractor | Base Bid | Alternate |
| DORNER, INC. | $3,751,956.86 | $4,019,356.56 |
| PETERS CONCRETE CO. | $3,828,285.89 | $3,989,479.94 |
| PTS CONTRACTORS, INC. | $3,950,182.93 | $4,199,826.68 |
| SOPER GRADING & EXCAVATING LLC | $3,962,615.23 | $3,996,134.37 |
| DEGROOT, INC. | $4,040,487.74 | $4,294,189.22 |
| ADVANCE CONSTRUCTION, INC. | $4,386,680.99 | $4,482,162.29 |