UPDATE: WORK RESCHEDULED

Find out what's happening in Glastonburyfor free with the latest updates from Patch.

As of 2/2, Eversource has informed the Town that this work has been POSTPONED from 2/3 and they plan to reschedule to Thursday, 2/10. The Town will continue to post updates as we receive further information/confirmation from Eversource.

Original Message:

Find out what's happening in Glastonburyfor free with the latest updates from Patch.

Beginning at 9:00 AM on Thursday, 2/3, the westbound lane of Hebron Avenue will be closed between House Street and New London Turnpike while Eversource conducts work in the area. Detour signs will be in place (see map below) and the eastbound lane of Hebron Avenue will be open, allowing access to all businesses, medical offices, and residences. The closure may be in place for up to 8 hours.

Detour Map

Please click here to see the detour map (or see image below) and plan travel accordingly this Thursday.

Please drive carefully and thank you for your patience as Eversource conducts this work.