DOT Updates – Niantic Drawbridge construction
Find out what's happening in The Lymesfor free with the latest updates from Patch.
DOT Project 44-154
Connecticut Department of Transportation Email Address: DOT.info.nianticriverbridge@ct.gov
05/04/20 Three-week Lookahead Plan
General
Label Piers for Identification 11-May-20 – 12-May-20
Find out what's happening in The Lymesfor free with the latest updates from Patch.
JOINT REPAIRS
Chip surface concrete(stairs) 5-May-20 – 22-May-20
Reconstruct Bridge endblock 25-May-20 – 27-May-20
Pier 05 Header and Joint Reconstruction 28-May-20 – 5-Jun-20
SUBCONTRACTORS
ETC Electric install temp power drop to trailer 13-Apr-20 – 15-May-20 25
Blast All begin moving in material 11-May-20 – 28-May-20