This post was contributed by a community member. The views expressed here are the author's own.

Neighbor News

Falmouth Wind Turbine Land Court Update 11/17/16

Falmouth is ground zero for poorly placed wind turbines USA. Expert disclosures were due 10/31/16. The deadline has been moved to 11/17/16

Town of Falmouth Wind Turbines Land Court November 17, 2016

The Town of Falmouth vs Falmouth Zoning Board of Appeals

Massachusetts Land Court

Find out what's happening in Falmouthfor free with the latest updates from Patch.

Attorney Chris Senie representing the plaintiffs has filed a motion to intervene in the Land Court case.

The court has approved the motion

Find out what's happening in Falmouthfor free with the latest updates from Patch.

Expert disclosures were due October 31, 2016. The deadline has been moved to November 17, 2016

A telephone conference call is scheduled for 11/17/2016 @ 10 AM

Notice sent to Attorneys Frank Duffy, Diane Tillotson, Christopher Senie and Mark Bobrowski

Expert Disclosures are due November 17, 2016

Joint Motion to Extend Deadline to File Expert Disclosures, ALLOWED.

Note # The Town of Falmouth continues to spend up to $300,000.00 every six months on litigation

Falmouth Wind I no longer is in operation

Falmouth Wind II only operates 12 hours a day six days of the week only when the wind blows

The Falmouth wind turbines are a health and financial fiasco .

Falmouth taxpayers : have been sold a bill of goods and they still don't get it !