Drakeshire Plaza Renovations 60-65 Percent Complete
Farmington officials approve a change order for the project, which needs some warmer weather to get moving again.

Renovations at Drakeshire Plaza, a privately owned shopping center that received assistance from the City of Farmington, are nearly two-thirds complete, city manager Vince Pastue told officials Monday.
City officials in October of 2012 narrowly approved an agreement with DIC Properties LLC to fund improvements on what has been a blighted and mostly vacant center. The DIC Properties is obligated to pay back the funds through an assessment.
During a Monday special study session, city council members approved a second construction estimate for the $335,600 contract with Richard Hyman Builders. It included a $2,980 change order; officials approved another $2,880 change order in December.
Find out what's happening in Farmington-Farmington Hillsfor free with the latest updates from Patch.
"There's a little more rotted area than anticipated," Pastue said, referring to structural damage that he said was not entirely unexpected.
Pastue said the project is 60 to 65 percent complete. A material being used on the exterior needs steady temperatures of over 40 degrees in order to cure, so workers may make additional progress is there is a warm stretch of weather in January.