Plymouth Twp. Road Construction Updates for April 9-14

Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., Jolly Rd., Apollo Rd., Township Line Rd., Hickory Rd. affected.

The Pennsylvania Turnpike Commission has released its weekly construction update for work on the "NE Extension Reconstruction and Widening Project" from the Mid-County Interchange to Berks Road.

According to the release, general impacts to the following areas include excavating, fence installation, clearing, stump grinding, crushing rock and hauling. Neighborhoods adjacent to the areas may experience "minimal noise impacts," the release says.

Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., Jolly Rd.
Excavating for mainline and retaining walls and installing sound barriers Monday, April 9th through Saturday, April 14th with shifts 24 hours a day.

Walton Rd., Apollo Rd., Township Line Rd.
Excavating for mainline, retaining walls, detention basins, sediment traps, and placing embankment Monday, April 9th through Saturday, April 14th with shifts 23 hours a day.

Hickory Road Mainline Bridge
Construction Monday, April 9th through Friday, April 13th from 7 a.m. to 6:30 p.m.

Township Line Road Mainline Bridge
Construction Monday, April 9th through Friday, April 13th from 7 a.m. to 6:30 p.m.