The Pennsylvania Turnpike Commission has announced in a release that the following areas in the Plymouth-Whitemarsh area will be under construction during the week of March 12:
Worcester Township
- North Wales Road, Crestline Drive, Deep Meadow Drive, Oak Terrace, and Shady Lane may be interrupted by crews excavating mainline from March 12 through March 17 from 7 a.m. to 5:30 p.m. and 8 p.m. to 5 a.m.
Whitpain Township
Find out what's happening in Plymouth-Whitemarshfor free with the latest updates from Patch.
- Jolly Road, Meadow Drive, and Mermaid Lake will be affected by excavating for retaining walls from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- Jolly Road, Meadow Drive, Wick Lane, and DeKalb Pike will be impacted by excavating mainline from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- Sheffield Drive, Larchwood Drive, and Old Arch Road will have crew excavating for retaining walls from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- Oak Ridge Drive, Rosewood Drive, and East Side Drive will be the sites of crew placing embankment and excavating for retaining walls from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- At Union Meeting Road and Jolly Road crews will be installing sound barrier posts and placing embankment from March 12 through March 16 from 7 a.m. to 5:30 p.m.
- Jolly Road Mainline Bridge will be the site of construction efforts from March 12 through March 13 from 7 a.m. to 5:30 p.m.
- Township Line Road Mainline Bridge will be the site of construction efforts from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- Wentz Road Mainline Bridge will be the site of construction from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- SEPTA Bridge will be affected by construction from March 12 through March 17 from 7 a.m. to 5:30 p.m.
Plymouth Township
- At Jocelyn Road and Hickory Road crews will be removing southbound privacy wall and constructing sedimentation basins from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- Walton Road, Apollo Road, and Township Line Road will be impacted by crews excavating retaining walls and the mainline and installing drainage from March 12 through March 17 from 7 a.m. to 5:30 p.m. and 8 p.m. to 5 a.m.
- Walton Rd., Fountain Rd., Allandale Rd., Colton Dr., Loretta Ln., Timberfare Cr., and Jolly Rd. will be the sites of crews excavating for mainline, detention basins and sediment traps from March 12 through March 17 from 7 a.m. to 5:30 p.m.
- Hickory Road Mainline Bridge will be impacted by construction from 7 a.m. to 5:30 p.m. from March 12 through March 17.