Politics & Government
Open House Set For $4.44M Alexandria Flood Mitigation Project
Residents can ask questions about drainage improvements and construction impacts Nov. 30 at Mount Vernon Recreation Center.

DEL RAY, VA — Residents can learn about the $4.44 million Hume Avenue Stormdrain Bypass Project and its expected construction impacts at an open house Monday, Nov. 30.
The meeting runs from 6:30 to 7:30 p.m. at Mount Vernon Recreation Center, 2701 Commonwealth Ave. City staff will present the proposed drainage improvements, discuss the construction schedule and answer questions.
The project will install a storm sewer along Hume Avenue to redirect runoff away from an existing pipe behind townhomes on the street's south side. New storm sewers and inlets along East Raymond Avenue are intended to capture water before it collects in low-lying areas.
Find out what's happening in Del Rayfor free with the latest updates from Patch.
Other work includes upgrading the sanitary sewer on East Raymond Avenue, restoring curbs and resurfacing Hume Avenue, and installing a backflow prevention valve beneath the Truist Bank parking lot on Mount Vernon Avenue.
The city lists $670,000 in federal grant funding toward the project. The contractor is expected to mobilize in December, with completion forecast for Nov. 1, 2027.
Find out what's happening in Del Rayfor free with the latest updates from Patch.
Additional information is available on the project page.