Rohnert Park Reminder: The Wheres and Whens of Traffic Projects

Two projects are starting Monday.

From the City of Rohnert Park:

TRAFFIC UPDATE - ROHNERT PARK EXPRESSWAY TREE WORK

LOCATION: Rohnert Park Expressway between Commerce Boulevard and Snyder Lane

CONSTRUCTION START: January 26, 2015

DURATION: Approximately 1 week

WORK BEING DONE: Mountain F will be trimming trees on Rohnert Park Expressway in the median between Commerce Boulevard and Snyder Lane in advance of the planned overlay of Rohnert Park Expressway.

************************************

TRAFFIC UPDATE - ADRIAN DRIVE WATER AND SEWER PROJECT

LOCATION: Adrian Drive between East Cotati and Santa Barbara

CONSTRUCTION START: Week of January 26
DURATION: Approximately 2 weeks

WORK BEING DONE: Cats4U and Team Ghilotti will be completing the final paving along Adrian Drive. Road closures will begin on Wednesday, January 28.

The work will require street closures and limited parking. Residents will be notified 72 hours in advance of parking restrictions. The City appreciates your patience as this work is completed.

************************************

TRAFFIC UPDATE - SNYDER LANE WIDENING PROJECT

LOCATION: Snyder Lane between Southwest Boulevard and Jasmine Circle

CONSTRUCTION START: Early February 2015

DURATION: Approximately 4 months

WORK BEING DONE: The City, with the school district’s permission, will be removing approximately 50 trees to allow for the widening of Snyder Lane. PG&E is expected to begin its work that will result in the undergrounding of overhead utilities in the same corridor.


************************************

TRAFFIC UPDATE - ROHNERT PARK EXPRESSWAY WATER MAIN
LOCATION: Rohnert Park Expressway from Snyder Lane to Petaluma Hill Road

CONSTRUCTION START: 1/19/15

DURATION: Approximately 5 months, through May 2015. (Inclement weather may prolong this timeframe.)

WORK BEING DONE: Argonaut Constructors is under contract with Brookfield Homes to install new utilities

************************************

On all of these projects, there will be lane closures and occasional traffic delays. Traffic control measures will be in place to move vehicles through the work zone in a safe manner. Pedestrian traffic control measures will also be implemented, including detours to adjacent sidewalks.

For your safety and the safety of the workers, please observe a 25 MPH speed limit through the construction area. Emergency access will be available at all times.

The City of Rohnert Park and the construction team greatly appreciate the public’s cooperation and patience during these disruptions.
The City of Rohnert Park Development Services can be reached at (707) 588-2232 orengineering@rpcity.org.