2013 Road Repair Project, Layer 2

The second layer (chip seal) will begin on Monday, September 23. This layer is a chip seal. The road will not be closed for hours (like the other layers) but there will be delays. Please use alternate routes, where possible.

You can download the schedule of streets below:

Find out what's happening in Watsonvillefor free with the latest updates from Patch.

2013RoadRepair2ndLayer (583.1 KiB)

Emergency vehicles will always have access. If you have questions, please call the Project Manager, Patrice Theriot, Principal Engineer at 768-3113

Thank you for your continued patience during this important project!