The County of  Santa Cruz has been working hard on the Salsipuedes Creek and Pajaro River Levee Projects. As of September 26th the following has been completed.

Salsipuedes Creek
  • Right bank surface work including asphalt concrete completed September 25th.
  •  Left bank surface work completed September 23rd.
  • Removal of perimeter silt fences completed September 25th.
  •  Smoothing out of aggregate base rock levee shoulders in progress.
  •  Hydroseeding of bare slope areas will begin October 7th.
  • Completion of construction / opening of levees on track for October 15th.
Pajaro River
  • Excavation and hauling completed August 23rd.
  • Hydroseeding of bare areas completed September 20th.
  •  Construction completed.

If you have questions regarding this project, you can contact Carisa Duran of the County of Santa Cruz Public Works Department at 454-2379.

THE PROJECT IS ON TRACK TO COMPLETE ALL CONSTRUCTION BY THE LAST CONTRACT WORKING DAY OF OCTOBER 15TH.