The $24 Million Winter Street Bridge Replacement project over Route 128 is in its 6th year of construction but major progress is being made across the project.
Over the Winter crews reached the biggest milestone yet when on January 9-11th before a massive snow storm hit crews placed the new concrete girders across all four spans. Work slowed down on the connections to the beams because of the extreme cold and the major amounts of snow. This past week crews started to place wood forms over the collector distributor roadway and will continue to place wood forms across all four spans for the rest of the month. Because of this each night for the Next 3 Weeks Route 128 NB & SB will be closed at Exit 27 at 11PM through 5AM. Crews are also working on grading the future eastbound lanes.
Biggest Change Coming to Second Avenue:
Find out what's happening in Walthamfor free with the latest updates from Patch.
After years of the constant changes at the Second Avenue & Winter Street intersection all that will come to an end. This past week crews have been installing electrical conduits for the new traffic signals, installed granite edging for a traffic island, poured a new concrete sidewalk and have been grading the Second Avenue intersection. Next week crews will be placing loom on the island and paving, installing curbing and other work at Second Avenue. According to the MassDOT by the end of April traffic will be shifted to its final alignment at Second Avenue.
Other Information:
Find out what's happening in Walthamfor free with the latest updates from Patch.
According to MassDOT work at the bridge is 70% Complete. McCourt Construction says all work on the bridge will be done by the end of August. All 7-lanes will be opened to traffic by September 1st 2011. Finish work around the project will carry into October.
By the end of 2011 a new bridge will finally be built across Route 128.