Northern Pass Hydropower Project Gets Key Presidential Permit
A 192-mile electricity transmission line would transport Hydro-Quebec energy from Pittsburg to Deerfield in New Hampshire.

CONCORD, NH — The Department of Energy granted the crucial Presidential permit for the $1.6 billion Northern Pass project that would carry hydropower from Canada and connect to the United States grid, powering about 1.1 million homes in southern New England. The project — first conceived in 2010 — calls for building a 192-mile electricity transmission line from Pittsburg to Deerfield in New Hampshire, to carry Hydro-Quebec energy.
The permit approval on Thursday is the latest sign of progress for the project, which has faced angry protesters and heated debates at scores of hearings. Supporters who say it will create jobs and slash energy costs have been pitted against those who fear the transmission lines will destroy scenic views, hurt property values and harm tourism.
"We are pleased to see the DOE permitting process for Northern Pass draw to a close, and appreciate the years of diligent work done by the federal agencies in reaching this critical project milestone," Bill Quinlan, president of the utility Eversource New Hampshire, said in a statement.
Find out what's happening in Across New Hampshirefor free with the latest updates from Patch.
"With the New Hampshire and Canadian permitting processes also nearing completion, and considering we have all major contractor, equipment and labor agreements in place, Northern Pass is on track to begin construction by mid-2018," he said. Quinlan added the progress is "good news" for customers and other interested parties "who support this project for the many benefits it will bring to the state and the region."
Republican Gov. Chris Sununu, who has long favored the project, said it would be a "home-run for small businesses, rate-payers, and clean energy advocates."
Find out what's happening in Across New Hampshirefor free with the latest updates from Patch.
"Today, New Hampshire is one step closer to lowering energy rates across the Granite State," he said in a statement.
Opponents said they were not surprised by the decision and are putting their hopes on a state group that also must weigh in on the transmission project. The New Hampshire Site Evaluation Committee, or SEC, is expected to announce its final written decision on the project by March 31, 2018.
Along with the state approval, the project also is awaiting a permit from the U.S. Forest Service allowing the project to pass through parts of the White Mountain National Forest and a wetlands permit from the U.S. Army Corps of Engineers, which is expected by the end of the year.
"They have a permit to cross the international border but they don't have a permit to site the project on 192 miles of New Hampshire landscape. That is what the SEC will determine," said Will Abbott, the vice president for policy with the Society for the Protection of New Hampshire Forests, which opposes the project.
"Their exuberance may be a bit premature," he said. "We believe the evidence makes a clear argument why the permit should be denied. We feel very confident that there is a very compelling argument for the SEC to get a decision not to issue a permit."
By MICHAEL CASEY, Associated Press