Politics & Government

Weather Delays Lake Lackawanna Dr. Reopening

Hopatcong drivers could use the road by next week, county official says.

Lake Lackawanna Drive might not open until the end of next week, a county official said.

The $677,066 Lubbers Run bridge rehabilitation project was supposed to end Nov. 25, but has been pushed back due flooding resulting from bad weather.

"It takes a long time to recover from the storms because the stream carries a lot of water," said Susan Delmar, supervising engineer of the Sussex County Division of Engineering. "It takes days for this particular stream to go down."

Find out what's happening in Hopatcong-Spartafor free with the latest updates from Patch.

Delmar said the Sussex County-funded project, which began Oct. 3 and was awarded to Jogi Construction of Edison, will result in a bridge that will last for more than 50 years.

Delmart said the road could open between Wednesday and Friday.

Find out what's happening in Hopatcong-Spartafor free with the latest updates from Patch.

Here's a list of objectives the project plans to accomplish.

    •    Installation of stream maintenance and soil erosion and sediment control measures
    •    Demolition of existing arch bridge and footings
    •    Excavation and construction of cast‐in‐place strip footings and pedestal walls
    •    Placement of precast arch units, spandrel walls and wing walls
    •    Install drainage and backfill precast units
    •    Apply stain/sealer and re‐place arch ring stones
    •    Roadway paving and striping
    •    Installation beam guide rail and fence
    •    Topsoil, seed and landscaping