Pickens High Conversion Passes OSF Inspection
Conversion of old Pickens High School into new site for Pickens Middle School on track; interiors could be complete before end of school year.
Changing the former Pickens High School into the new home of Pickens Middle School students cleared a significant milestone last month.
The project passed inspection by the Office of School Facilities, according to district spokesman John Eby.
Eby took me on a tour of the school Friday afternoon.
Find out what's happening in Easleyfor free with the latest updates from Patch.
New school construction and the renovation of existing schools are being done with safety at the forefront. Β
βFrom Day 1, kids will be safer in the new school,β Eby said.
Find out what's happening in Easleyfor free with the latest updates from Patch.
All visitors will be funneled to the front office.
βThe thing that theyβre trying to install inside all the schools β¦ is a buzzer (at the entrance, to where you buzz in and tell the receptionist why youβre here,β Eby said. βAnd the receptionist can see you while youβre talking to her, then they let you in. Thatβs what weβre trying to go to for secure entries for all the new schools, is a buzzer system like that.βΒ
The doors leading beyond the office into the school itself βare locked all the time,β Eby said.
That will prevent visitors from getting into the school undetected.
βAnybody entering the school goes through the reception area here,β Eby said.Β βNobody can be going in through the side doors.β
βItβs just a commentary on the way the world has changed in fifty years, since a lot of the old schools were built,β Eby said. βIt was a time when people didnβt think of a school as a target. I think then the biggest safety concern would be, βHow many different ways can kids get out, say, in a fire?β
βYou still have to maintain that concern,β he continued. βYou still have to have the multiple exit areas. Itβs just that they all have to be set up to be locked all the time, outside this one door.β
School staff are βthinking in a security mindset, all the time,β Eby said. βSometimes security and convenience are at odds.β
While you can never predict a given attack, you can take steps to impede an intruder β while police are en route to the school.
βAnything you can down to slow an intruder can save lives,β Eby said.
The schoolβs old gym has been transformed into the middle schoolβs new cafeteria.
βThis is my favorite part of the building,β Eby said. βI call Grand Central Station because of the windows got up there. When the sun is shining at the right time of day with the right light, you get those beams of light coming in through those top windows. It looks really nice.β
Acoustical chevrons in the cafeteria and choir and band rooms will help keep sound from drifting into other areas.
The orchestra room at the existing middle school is βhalf the sizeβ of the new orchestra room. The conversion is also providing the orchestra with some much-needed storage space.
Eby said his father recently retired from the music department at Bob Jones University.
βThey had a brand-new fine arts building, university-level, and their band facilities were not better than this,β Eby said.
Cafeteria equipment is β100 percent new.β
Some rooms and facilities are a mixture of old and new, taking advantage of items such as flooring βthat were built to last,β Eby said.
The conversion program is giving a new look and new life to a building that has been serving the district and students for generations.
βIt looks like it was built yesterday,β Eby said.
Teachers will move their supplies in over the summer.
βTheyβre more than safely on pace to be in here in time for school to start,β Eby said. βI think everything in this building will be done before weβre done with this school year.β
Last week, Bob Folkman, district building program director, told board members the building program is β94 percent complete.βΒ